Tag Archives: Safety and Health Ordinance

Managing safety and health at metal scaffolding work

Managing safety and health at metal scaffolding work

A safety management system and a safe system of work should be developed, implemented and maintained for the safety and health at work of workers. Further reference should be made to the Factories and Industrial Undertakings (Safety Management) Regulation. Among other things, the following actions should also be taken into account:

4.1  Design and initial planning

A  construction   project   should   be   designed   with   safety   in   mind.   This approach makes it possible to eliminate or minimize the work hazards by proper planning and design of the methods of construction, sequences of activities, coordination, etc.

4.1.1  During the design of a metal scaffold, attention should be paid in the following areas:

(a)   The safe scaffold and its erection/alteration/dismantling for all different stages of construction should be designed and planned well beforehand.

(b)     The  safe  method  of  scaffolding  devised  should  be  kept  under continual review.

(c)     The strength and stability of the scaffold throughout all stages of scaffolding should be ensured.

(d)     The strength of scaffolding members such as tubes and couplers should be ensured. Reference should be made to the procedures laid down in relevant standards of the International Organization for Standardization or equivalent procedures for their sampling and mechanical testing.

(e)    Realistic  assessment  of  loadings  on  the  scaffold  at  all  work stages should be made. In considering the wind load on the scaffold, reference should be made to the Code of Practice on Wind Effects in Hong Kong, 2004 (Buildings Department).

(f)      Safe  access  to  and  egress  from  the  working  places  should  be provided.

(g)    Effective  bonding  system  to  earth  should  be  provided  to  the scaffold.

(h)    Additional  features  such  as  attachment  points  for  ladders, working platforms, guard-rails and toe-boards should be provided for the protection of workers using the scaffold. Safety nets and safety belts should also be provided for the protection of scaffolders.

(i)      Scaffolding  components/materials/equipment  should  be  handled, lifted, stored, stacked and transported safely.

(j)      The time when the scaffold would be erected and dismantled should be decided in the design and planning stage. The scaffold should be dismantled as soon as it is no longer required to be used.

4.1.2  Specification for scaffolding contract document:

(a)     Specification     for     scaffolding     contract     document     should incorporate    particular   requirements   and   essential   information for the scaffolding work to be planned and implemented safely. (For example,  the  provision  of  design  drawings  and  method statement; phasing of work – particularly with other contractors; periodic maintenance and repair of scaffold.)

(b)    Special   requirements   relating   to   compliance   with   safety legislation should be highlighted and, where appropriate, these items should be included in the Bills of Quantities.

(c)     Depending on the size of the project and/or the complexity of the work involved, tenderers for the scaffolding work should be required to submit an outline scaffolding plan at tendering stage, giving sufficient information to demonstrate their intended safe system of work.

4.1.3  Coordination and communications:

(a)     There should be close liaison between all relevant parties even at the design and planning stage.

(b)     Effective lines and systems of communication should be devised for each stage of the scaffolding work and a person should be assigned to maintain effective communication.

4.1.4  Initial planning:

(a)    Site considerations and risk assessment

Potentially  hazardous  site  features  and  other  aspects  likely  to impair safe scaffolding should be identified. The risk arising from each individual hazardous event should be evaluated according  to its probability and consequence. The following special conditions of the site should be taken into account:

(i)     The existence of overhead electric power lines.

(ii)    The   existence   of   overhead   signboards   or   projections,

particularly those in the urban areas.

(iii)    The  existence  of  buried  services,  including  underground electric cables, gas or other fuel pipelines.

(iv)   The existence of storage tanks.

(v)    Restricted access to, and onto the site.

(vi)    Restricted space for erection, manoeuvring, storage and, if required, for on-site pre-assembly or fabrication.

(vii) Low ground bearing pressures that may be due to, for example, made ground or existing underground services or structures.

(viii) The proximity and condition of other buildings and premises that may by itself or so-induced special wind effect (for example, funnelling effect) affect the planned method of scaffolding.

(ix)   The shape and the structure of the building. (x)    The juxtaposition of the public and the site. (xi)   The activities of other contractors.

(xii)  The  existence  of  noxious  gases,  chemicals,  fluids  or  dust

emitted from processes on or around the site.

(xiii) The proximity of the site to seashore where the strength of the scaffolding may be affected by seawater.

(b)    Preliminary method statement

The preparation of a preliminary method statement is an important part of planning for a safe system of work in scaffolding. Where appropriate, a preliminary method statement should include:

(i)      the arrangements for coordination and the responsibilities and authority of supervisory personnel during scaffolding work;

(ii) the scaffolding sequences including erection and dismantling;

(iii)    the  methods  of  ensuring  stability  with  due  consideration of future construction activities (for example, trench work, external building services /facilities installation);

(iv)    the detailed scaffolding work method which should ensure that the work could be carried out safely;

(v)    the construction tolerance;

(vi)    the assessed maximum allowable loading (includes vertical and lateral loads) on the scaffold/working platform;

(vii)  the provisions to prevent falls from height, including safe means

of access and egress and safe places of work;

(viii) the protection from falls of materials, tools and debris, and the

provision of catch-fans and protective screens at the scaffold;

(ix)   the provision of suitable plant, tools and equipment;

(x)    the   arrangements   for   delivery,   stacking,   storing   and movement on site for scaffolding components, materials and equipment;

(xi)   the details of site features, layout and access; and

(xii)  the contingency arrangements.

4.2  Selection of subcontractor for metal scaffolding work

4.2.1  If   a   subcontractor   is   to   be   engaged   in   metal   scaffolding   work, whether he would make adequate provisions for safety and health should be an important selection consideration. Selection criteria should also include the ability of the subcontractor in providing a good scaffolding plan.

4.2.2  During the process of selection, the subcontractor should be required to submit an outline scaffolding plan, giving preliminary information to demonstrate the intended safe system of work. Depending on the complexity of the project, the outline scaffolding plan should briefly describe items such as safety organization, communication, monitoring, equipment, facilities, emergency procedures, accident reporting, and accident investigation procedures.

4.2.3  After the subcontractor has been appointed, he is required to finalize a detailed scaffolding plan on the basis of the outline scaffolding plan if any, for agreement in writing. The detailed scaffolding plan should spell out the ways and means to carry out work safely and effectively in order to fulfil the objective of protecting workmen at work. The detailed scaffolding plan should also be incorporated into the safety plan of the main project.

4.3  Site management and procedures

4.3.1  Managing for safe erection/alteration/dismantling

Safe  working  methods  and  practices  on  site  should  be  ensured  as follows:

(a)    Preparation and use of a detailed method statement

The extent of detail in a detailed method statement will depend upon the size and/or complexity of the work, with a simple job requiring a simple method statement and repetitive tasks being covered by standard sheets. Preliminary method statement produced at the planning stage should be developed into a detailed method statement that should be incorporated into the detailed scaffolding plan. The whole method statement should be reviewed and updated as necessary so that it remains current. It should be distributed to all those concerned with the supervision of scaffolding work.

(b)    Thorough and active contract coordination both on and off site

Coordination and liaison between parties should be maintained throughout the job. Any changes in previously agreed procedures must  be  verified  by  the  person  responsible  for  coordination  as being safe before they are implemented. Matters that will contribute to safe scaffolding work on site, including the availability of information, plant and manpower, and the quality and supply of materials should also be coordinated.

(c)    Implementation and maintenance of effective communications

To  ensure  that  precautions  for  safe  scaffolding  outlined  in  the method  statement  are  followed,  lines  of  communication  should be clearly designated, with the responsibility for implementing the method statement well defined.

(d)    Contingency plan for adverse weather conditions

Weather conditions that could have an adverse effect on the scaffolding work such as rain, high wind, lightning or typhoon, and those causing poor visibility, such as fog, mist or glare should be constantly monitored.

If  a  decision  is  made  to  stop  work,  then  measures  should  be taken to maintain the stability of the scaffold and the plant, equipment and works erected on the scaffold.Also, all personnel should be safely and efficiently evacuated from the scaffold. After the adverse weather, the scaffold should be inspected and certified in safe working order by a competent person and all the plant, equipment and works erected on the scaffold should be checked and confirmed to be in order before work is to be restarted.

(e)    Provision of suitable staff

No scaffold shall be erected on the site or substantially added to, altered  or  dismantled  except  under  the  immediate  supervision of a competent person and by trained workmen possessing adequate experience of such work (Regulation 38E of the CSSR). Training should be a continuing process with on-the-job instruction and formal training sessions provided as appropriate (refer to Section 4.6).

(f)     Provision of protective equipment

Protective  equipment  that  is  necessary  and  appropriate  for  the work  should  be  provided.  Examples  of  protective  equipment are: safety helmets, safety nets and safety belts with suitable anchorage.

4.3.2  Preparing the site and the work

(a)     Plans  and  drawings  should  be  checked  for  matters  relating  to scaffolding safety before work is to be started.

(b)     The need to exclude other personnel from scaffolding areas when scaffolding work is in progress should be considered.

(c)    Site   inspection   should   be   conducted   to   check   the   physical

conditions, the hazards involved and other special features. (d)    The ground condition should be made firm, level and suitable.

(e)    The  maximum  safe  loading  (includes  vertical  and  lateral  loads)

imposed on the scaffold should be assessed, and strictly adhered to.

(f)      The scaffolding members should be checked for their fitness before despatching to the site. Defective materials should be prohibited to be used and should be removed from site as soon as possible. During their stay on site pending for removal, they should be properly labelled to show that they are defective and should not be used.

(g)    A suitable  place  should  be  provided  at  the  site  for  storage  of scaffolding members and the associated materials, tools or equipment. Also, they should be properly stacked and tied to prevent accidental displacement and collapse. The storage area should be clearly shown on the site plans.

(h)     Documents  such  as  scaffolding  plan,  method  statement,  design drawings and specifications of the scaffold, etc. should be made available to all parties concerned in good times.

4.4  Working places and access

4.4.1  Working platform of scaffold

(a)     A  method   statement   for   construction   of   a   working   platform should be devised. Please refer to Section 4.3.1 (a) on method statement.

(b)    Guard-rails  and  toe-boards  shall  be  installed  at  edges  where persons are liable to fall from height. The guard-rails shall have adequate  strength  and  be  securely  fixed.  The  height  of  a  top guard-rail  shall  be  between  900mm  and  1 150mm  above  the platform.  The  height  of  an  intermediate  guard-rail  shall  be between 450mm and 600mm above the platform. The height of a toe-board shall be not less than 200mm (Third Schedule to the CSSR).

4.4.2  Safety net

Provision of a workplace without risk of falling should always be the first consideration. However, if this is not practicable, safety nets and safety belts shall be used (Regulation 38H of the CSSR). Reference should be made to national/international standards or provisions for the standards of safety nets and safety belts.

4.4.3  Safety belt

In all the circumstances of the case, if it is impracticable to provide safety net, wearing of safety belt with effective anchorage system is required as the last resort for fall prevention (Regulation 38H of the CSSR). Further reference should be made to the Guidance Notes on Classification and Use of Safety Belts and their Anchorage Systems prepared by the Labour Department. It is strongly recommended that, when a choice of safety belt is possible, a safety harness incorporating buttock straps, as distinct from a general purpose safety belt, should be used.

4.4.4  Provision of catch-fan and protective screen

(a)    At  least  a  sloping  catch-fan  at  not  more  than  15m  vertical

intervals  to  give  a  minimum  horizontal  projection  coverage  of

1 500mm  should  be  provided.  The  sloping  catch-fan  should consist  of  timber  boarding  and  a  layer  of  galvanized  metal sheeting, both of adequate thickness to capture and retain falling objects.

(b)     A suitable receptacle should be provided within each catch-fan to trap falling objects. The weight of the receptacle should not affect the stability of the catch-fan.

(c)     The sloping catch-fan and receptacle should remain in place until all works are completed.

(d)     On  the  face  of  the  scaffold,  suitable  protective  screen  of  fire retardant  material  should  be  provided  to  confine  falling  objects. If tarpaulin is being used as protective screen, its fire retardant characteristic should meet the requirements of BS 5867-2:2008 (Type B performance requirements) or other equivalent national/ international standards or provisions.

4.5  Monitoring safety performance

4.5.1 Requirements on safety and health, particularly those relating to compliance with safety legislation, are advisable to be incorporated into the conditions of contract for engagement of subcontractor for metal scaffolding work or other subcontractors using the scaffold.

4.5.2  Regular records on the safety conditions of the scaffolding should be kept.

Such records should consist of detailed information on work hazards, precautions taken, accident analysis and recommendations. These records should be constantly reviewed for hazard identification and improvement.

4.5.3 Workmen’s feedback on the safety conditions of the site should be encouraged and as far as possible documented.

4.5.4 A monitoring system should be developed, implemented and maintained on site for checking the safety performance of the subcontractor for metal scaffolding work or other subcontractors using the scaffold against the requirements mentioned in Section 4.5.1.

4.6  Training of metal scaffolders

4.6.1  The objective of training is to increase the efficiency of workers and to improve safety performance in erecting, altering, maintaining and dismantling scaffolds. The importance of ensuring that workers who erect, alter, maintain and dismantle scaffolds are fully competent is obvious, but the degree of skills which are required differ according to the duty to be performed. There is a great span of proficiency and experience required. Properly controlled training is therefore vital for safety and it would eventually attract a better type of man to make a career in the industry. Before training of the scaffolders is to be considered, they should be physically fit for the scaffolding work first.

4.6.2  Training  of  scaffolders  needs  to  relate  to  basic  site  safety,  familiarity with everyday hazards and the requirements for a safe place of work. In general, training for scaffolders should start at ground level, where basic  skills  can  be  acquired,  and  when  scaffolders  are  proficient, using   those   skills   at   increasing   height   would   be   appropriate. Training should continue after basic skills have been acquired to ensure that scaffolders  are  familiar  with  improvements  in  techniques,  the  use of  newly  developed  equipment/materials,  and  to  ensure  that  safe methods of work continue to be used.

4.6.3  When   a   new   scaffolder   is   employed,   the   management   should ascertain the previous safety training of him, and should not assume that any scaffolder has a particular skill or training without seeing some proof or demonstration. Induction training will be needed to explain such matters as the company’s safety policy/organization, company safety rules, accident reporting requirements, etc. Besides, training/instruction would be necessary when the new scaffolder first starts on a project, to cover the particular requirements of the site such as emergency procedures, any special hazards and the safety aspects of the scaffold.

 

Issue of improvement notice and suspension notice under the Occupational Safety and Health Ordinance

Issue of improvement notice and suspension notice under the Occupational Safety and Health Ordinance

3.3.1  Section 9

This section empowers the Commissioner to serve on an employer or an occupier of premises where a workplace is located an improvement notice requiring the rectification of contravention against safety legislation within a specified period.

3.3.2  Section 10

This  section  empowers  the  Commissioner  to  serve  on  an  employer who   is   responsible   for,   or   an   occupier   of,   premises   where   a workplace is located a suspension notice requiring suspension of an activity or use of premises or of any plant or substance where there is an imminent risk of death or serious bodily injury.